Liquidated Damages Calculator (Contract Delay Penalty)

Calculate the liquidated damages for delay from the contract value, daily penalty, days of delay and cap. Find out whether the penalty is proportionate to the real damages and enforceable in common law and civil law. Parametric, currency-neutral.

Calculation parameters
Was this calculator useful?

How much is a liquidated damages clause for delay worth, and — a question often overlooked — is it actually valid and enforceable? The liquidated damages clause (a «penale contrattuale» in Italian) is one of the most used tools in contracts: an amount, agreed in advance, that one party must pay the other if it fails to meet the terms, typically for a delay in delivery or performance. It serves to avoid having to prove the loss suffered in court: the parties fix the number beforehand, and in case of delay it applies automatically. This calculator does two things. First, it calculates the amount of the liquidated damages from the contract value, the daily penalty, the days of delay and any cap. Second — and this is what makes it premium — it assesses whether the penalty is proportionate to the real damages, because a penalty that is too high risks not being valid: in common-law systems it can be declared unenforceable as a «penalty», in civil-law systems it can be reduced by the court. It is a parametric, currency-neutral tool, valid across multiple jurisdictions: enter your numbers and understand not only how much, but whether and how the penalty will hold up.

What liquidated damages are

Liquidated damages is a provision by which the parties establish in advance the amount that will be owed in case of breach — very often a delay in the delivery of a work, a supply or a service. The name means «damages settled» in advance, i.e. quantified beforehand. Its function is twofold and elegant. On one hand it avoids having to prove the loss: without a liquidated damages clause, the party harmed by a delay would have to demonstrate in court how much it actually lost — a long, costly and uncertain process. With the clause, the amount is already agreed: the delay triggers, the penalty applies. On the other hand it gives certainty to both parties: the one performing the contract knows in advance how much it risks if it is late, and can price it; the one commissioning knows how much it will recover. In many contracts, moreover, the clause also works as a limit on liability: the breaching party pays no more than the liquidated damages, even if the real loss were greater. This dual nature — simplification of proof and limit of liability — is what makes the liquidated damages clause so widespread in construction, supply, IT contracts, procurement and M&A. But its validity is not a given, and depends on how it is calibrated relative to the real loss, as we will see.

How it is calculated: daily penalty, delay, cap

The calculation of the delay penalty is based on a few clear elements. The first is the contract value, the base on which the penalty is often measured. The second is the daily penalty: the amount owed for each day of delay, which this calculator expresses as a percentage of the contract value per day (a common and currency-neutral form; typically between 0.05% and 0.2% per day, but it varies a lot). The third is the number of days of delay. Multiplying the daily penalty by the days gives the accrued penalty. The fourth element, crucial, is the cap: almost all well-written contracts limit the total penalty to a percentage of the contract value (often 5-15%), to prevent a long delay from leading to disproportionate amounts. The penalty actually owed is therefore the lesser of the accrued penalty and the cap. The fifth element is not used to calculate the amount, but for the assessment: the estimated actual damages from the delay, which allow judging whether the penalty is proportionate. In formula: daily penalty = value × daily percentage; penalty owed = minimum between (daily penalty × days) and (value × cap%). The calculator returns the penalty owed, the accrued one, its share of the contract and the days beyond which the cap kicks in.

The breakdown of the calculation

The table shows the breakdown in the default case — contract 500,000, daily penalty 0.1%, delay 40 days, cap 10%, estimated damages 30,000:

ItemValue
Contract value500,000
Daily penalty (0.1%)500 per day
Days of delay40
Accrued penalty (500 × 40)20,000
Cap (10% of 500,000)50,000
Penalty owed (lesser of the two)20,000
Share of the contract4%
Days to reach the cap100
Ratio to estimated damages (20,000 / 30,000)~0.7

The picture is clear. With 40 days of delay, the accrued penalty is 20,000, well below the cap of 50,000, so it is the one owed — 4% of the contract value. The cap would kick in only after 100 days of delay. And, decisively, the penalty (20,000) is lower than the estimated damages (30,000): a ratio of about 0.7, which places the clause in the most solid zone from a legal standpoint. Change the values with yours: you will immediately see the amount, but also — thanks to the comparison with the real damages — whether the penalty is calibrated in a defensible way or risks being considered excessive. It is precisely this comparison that is the heart of the assessment, as we explain in the following sections.

Liquidated damages or penalty: the key distinction

The most important legal point to understand is the difference between a legitimate liquidated damages clause and a penalty clause. The distinction is ancient and universal, and it decides whether the clause holds up. A clause is a legitimate provision of liquidated damages when the agreed amount represents a reasonable pre-estimate of the loss expected from a breach, made at the time of signing. In this case it has a compensatory function — it anticipates and simplifies the compensation — and is fully valid. A clause is instead a penalty (in the pejorative sense) when the amount is disproportionate to the foreseeable loss, to the point of having a function that is not compensatory but intimidatory or punitive: it serves to «terrorize» the counterparty, not to compensate a loss. The criterion, in many legal systems, is not whether the amount turned out to be high in hindsight, but whether it was a genuine estimate of the loss at the time of the agreement. This distinction has enormous practical consequences: a clause qualified as a penalty can be struck down — declared unenforceable or reduced, depending on the legal system. That is why the comparison between the penalty and the real expected damages is not an academic detail, but the test that determines whether your clause will be worth something when you need it. This is a parametric estimate, not legal advice.

Common law vs civil law: two approaches

The way an excessive penalty is treated depends on the legal system, and here the two great world models diverge in a fascinating way. The table compares them:

AspectCommon law (UK, US, etc.)Civil law (Continental Europe, Latin America, etc.)
Penalty clause valid?Yes, if it is a genuine estimate of the lossYes, generally allowed
If disproportionate?«Penalty»: risks being unenforceableThe court can reduce it to a fair amount
Typical outcomeAll or nothing (valid or void)Reduction (stays valid but corrected)
CriterionGenuine estimate at the time of signingManifest excessiveness (or derisoriness)

The difference is profound. In common-law systems (United Kingdom, United States, many Commonwealth countries) the «penalty doctrine» historically applies: a clause that is a genuine pre-estimate of the loss is valid and enforceable, but a clause that appears punitive is considered a «penalty» and is not enforced — the harmed party goes back to having to prove the actual damages. It is an «all or nothing» approach: the clause holds up or falls. In civil-law systems (much of continental Europe, Latin America, and beyond) the approach is more flexible: the penalty clause is allowed, but the court typically has the power to reduce it if it deems it manifestly excessive (and sometimes to increase it if derisory). The clause does not fall, but is «corrected» to a fair amount. For those drafting international contracts, the consequence is practical: the governing law of the contract changes the fate of an excessive penalty. In a contract governed by English law, a disproportionate penalty can be zeroed; in one governed by a civil-law system, it would probably be reduced. Knowing which system applies is essential to calibrate the clause. This is a parametric estimate, not legal advice.

The cap: why it protects both sides

Almost every well-written penalty clause provides for a cap, typically a percentage of the contract value (often 5-15%). The cap has a role that protects, surprisingly, both parties. For the one performing the contract, the cap limits the exposure: however long the delay, the penalty will not exceed a certain threshold. Without a cap, a very long delay could theoretically make the penalty grow to ruinous amounts, and this would make the risk impossible to price or insure. For the one commissioning, paradoxically, the cap helps the validity of the clause: an unlimited penalty is much more likely to appear punitive and be struck down, while a reasonable cap signals that the clause has a compensatory, not intimidatory, function. There is, however, an important flip side to understand: once the cap is reached, every further day of delay costs nothing more in terms of penalty. This changes the incentives: past that threshold, the delaying party no longer has an economic reason (from the penalty) to speed up, and the harmed party might find it more convenient to terminate the contract than to keep waiting. The calculator shows precisely after how many days of delay the cap kicks in: it is strategic information, not just accounting. This is a parametric estimate, not legal advice.

The penalty as pre-estimate and as limit

An often-misunderstood aspect is that the penalty clause cuts both ways: it helps whoever invokes it, but also limits them. On one hand, as we have seen, it simplifies enormously: the harmed party does not have to prove the loss, it is enough to demonstrate the delay and apply the agreed amount. It is a huge procedural advantage. On the other hand, however, in many legal systems and many contracts the penalty also represents the cap on compensation: if the real loss turns out to be higher than the penalty, the harmed party cannot — barring different provisions — claim more. It accepted that number, and that number acts as a limit. This means that a penalty that is too low is not a validity problem (no court will strike it for being too mild), but it can be an economic problem for the one commissioning: if a delay can cause damage far greater than the penalty (for example the loss of a downstream customer, or penalties you yourself pay to third parties), setting a low penalty means waiving that part of the compensation in advance. That is why calibration is a balance: high enough to compensate the realistic loss and incentivize timeliness, contained enough to remain a defensible estimate and not a penalty. The comparison between the penalty and the estimated real damages, which the calculator puts at the center, serves exactly to find this balance. This is a parametric estimate, not legal advice.

Penalty vs actual damages: the proportionality test

The heart of this calculator's assessment is the ratio between the penalty and the estimated actual damages. It is the proportionality test that, in one form or another, all legal systems apply to decide whether a penalty clause is legitimate or abusive. The logic is simple: the penalty should be a reasonable estimate of the loss expected from a breach. If the ratio is close to 1 (penalty ≈ damages), the clause reflects its compensatory function and is valid almost everywhere. If the penalty is moderately higher than the damages (ratio up to about 2), it generally remains reasonable, but the zone where proportionality matters begins. If the penalty is much higher than the damages (ratio over 2-4), the risk grows: in common law it could be classified as a penalty and fall, in civil law reduced by the court. If the penalty is enormously disproportionate or if the expected damages are almost nil, the clause has all the characteristics of a punitive penalty and is at high risk. Beware: the correct criterion looks at the estimate at the time of signing, not at what actually happened. A clause well calibrated on the foreseeable loss at the outset remains valid even if, with hindsight, the concrete loss was smaller. Documenting why a certain loss was expected (fixed costs, downstream penalties, reputational losses) is the best defense. The calculator shows you where you stand on this scale. This is a parametric estimate, not legal advice.

When the penalty risks being invalid

Putting the concepts together, there are some typical situations in which a penalty clause risks not holding up. The first and most common: the penalty is manifestly disproportionate to any foreseeable loss — the classic case of the punitive clause. The second: the expected damages were almost nil at the time of signing, so that any amount appears without anchoring to a real loss. The third: the clause is worded to hit any breach, even minimal, with the same high amount — a single large number for breaches of very different gravity suggests an intimidatory function. The fourth: a cap is entirely missing, and the penalty can grow indefinitely. Conversely, the elements that strengthen validity are the mirror image: an amount anchored to a documented estimate of the loss, a reasonable cap, a graduation (different penalties for delays or breaches of different gravity), and consistency between the penalty and the value/risk of the contract. A practical tip: when drafting the clause, keep a written record of the reasoning that leads to the chosen amount (why that loss was foreseeable). If one day the clause is challenged, that documentation is the proof that it was a genuine estimate and not an intimidatory penalty. The calculator helps you test the proportionality before a court does. This is a parametric estimate, not legal advice.

Types of penalty and contracts

Penalty clauses for delay appear in many types of contract, each with its own characteristics. The table summarizes the most common contexts:

ContextTypical use of the penalty
Procurement and constructionDelay in the completion of the work (per day)
Supply and saleDelay in the delivery of goods
IT and software contractsDelay in release, failure to meet service levels
Services and outsourcingFailure to meet deadlines or SLAs
M&A and closingDelay in completing the transaction
Events and productionDelay in delivery on a fixed date

The most classic context of use is that of procurement and construction, where delay penalties (often «per day of delay») are a consolidated standard: a delayed project generates costs and losses for the client, and the penalty anticipates them. But the tool is universal. In supply, the penalty covers the delay in the delivery of goods. In IT and software contracts, it applies to the delay in release or the failure to meet agreed service levels (where the delay penalty intertwines with SLA penalties). In services and outsourcing, it sanctions the failure to meet deadlines. Even in M&A transactions similar mechanisms appear for delay in the closing. In every context the same principles of proportionality and validity that we have seen apply: the object changes, not the legal logic. The calculator is parametric precisely to adapt to any of these scenarios: enter the contract value and the penalty terms of your specific case. This is a parametric estimate, not legal advice.

How to draft a good penalty clause

Drafting an effective penalty clause is a balance between deterrence and validity. Some principles help. Anchor the amount to an estimate of the loss: start from how much you realistically lose in case of delay (additional costs, lost revenue, penalties you pay to third parties) and calibrate the penalty on that basis, keeping a written record. Provide for a reasonable cap: it protects the performer and strengthens validity. Graduate when it makes sense: different penalties for delays of different duration or gravity are more defensible than a single amount for everything. Be clear about the mechanism: when the delay starts running, how it is calculated, when it applies, and whether the penalty is the only remedy or adds to others. Clarify the relationship with compensation: is the penalty exclusive (cap on compensation) or does it accumulate with further damages? It is a choice with great consequences. Consider the governing law: in an international contract, the choice of governing law influences how an excessive penalty will be treated. Avoid the punitive aspect: amounts that appear intimidatory, or that hit every minimal breach with the same severity, are the most fragile. The golden rule is that a good penalty clause should not «scare», but credibly compensate a foreseeable loss. The calculator helps you verify that the chosen amount is proportionate; the precise drafting requires the assistance of a lawyer. This is a parametric estimate, not legal advice.

Limits of the calculation

This calculator provides a parametric estimate of the amount of a delay penalty and an indicative assessment of its proportionality, not legal advice nor a prediction of how a court will decide. The model simplifies reality in several ways. It calculates the penalty as daily penalty times days, with a cap: many real clauses are more articulated (graduated penalties, thresholds, delay grace periods, different calculation mechanisms). The validity assessment is based on the ratio between penalty and estimated damages alone, whereas the real legal qualification depends on many factors (the exact wording of the clause, the governing law, local case law, the concrete circumstances, the bargaining power of the parties). The estimated actual damages are precisely the most difficult and subjective element: quantifying the loss expected from a delay requires analysis, and the legal criterion looks at the estimate at the time of signing, not at what happened afterward. The differences between legal systems are presented in simplified form; each system has its own rules and nuances. Use the result to understand the order of magnitude of the penalty and to get an idea of its risk profile (proportionate or potentially excessive), but to draft, negotiate or challenge a penalty clause turn to a lawyer competent in the governing law. This is not legal advice.

Example: how the penalty grows with the days of delay

To understand the effect of the cap, it helps to see how the penalty grows as the delay increases, until it stops at the cap. The table uses the default case (contract 500,000, penalty 0.1%/day = 500 per day, cap 10% = 50,000):

Days of delayAccrued penaltyPenalty owed (after the cap)
105,0005,000
2010,00010,000
4020,00020,000
8040,00040,000
10050,00050,000 (cap reached)
12060,00050,000 (frozen at the cap)

The table clearly shows the dynamic. Up to 100 days, the penalty grows linearly by 500 per day, following the delay. At 100 days it reaches the cap of 50,000 (10% of the contract). From then on, however long the delay continues — 120 days, 200 days — the penalty stays frozen at 50,000: the cap freezes it. This has an important strategic implication, worth emphasizing. Before the cap, the penalty is a growing incentive to recover the delay: every day costs. After the cap, that incentive disappears: for the delaying party, the 101st day and the 200th cost the same (zero additional penalty). For the harmed party, this is the moment to reassess the options: if the delay approaches or exceeds the days-to-cap and the damage keeps accumulating, the penalty alone is no longer enough to protect you, and other avenues — from terminating the contract to an action for further damages (where allowed) — become relevant. That is why the calculator highlights the «days to reach the cap»: it is the threshold beyond which the logic changes. This is a parametric estimate, not legal advice.

Penalty vs contract termination: when it is worth it

Once the mechanism of the cap is understood, a strategic decision that is often overlooked emerges: at a certain point, faced with a prolonged delay, the harmed party must ask whether it is better to keep waiting (collecting the penalty) or terminate the contract and seek another solution. As long as the penalty grows (before the cap) and the counterparty is actually working to complete, waiting can make sense: the penalty compensates the delay and in the end you get what you contracted for. But when the cap is reached, the balance changes: the penalty no longer grows, while your real damage keeps accumulating (costs, lost revenue, missed opportunities). At that point, continuing to wait means suffering growing damage against a frozen compensation. Termination becomes a serious option: closing the relationship, collecting the accrued penalty, and turning to another supplier or another solution can be more convenient than waiting indefinitely. The decision depends on many factors: how close you are to completion, how much it costs and how feasible it is to find an alternative, the contract's termination clauses, and whether you can accumulate the penalty with compensation for further damage. There is no universal answer, but the principle is clear: the penalty is a powerful tool up to a certain point, beyond which other contractual remedies become more relevant. Knowing where the cap kicks in helps you recognize that point. This is a parametric estimate, not legal advice.

Penalty and SLAs: penalties in service contracts

An area where penalties are particularly widespread and structured is that of service contracts with guaranteed service levels (SLAs). In an SLA contract — typical of IT, cloud, telecommunications and outsourcing — the provider commits to maintaining certain standards (for example 99.9% availability, or maximum response times), and provides for penalties (often called «service credits») if it fails to meet them. The logic is the same as the delay penalty: a predefined amount that triggers when a measurable breach occurs, avoiding having to quantify the damage case by case. There are, however, some peculiarities. SLA penalties are often structured as credits (discounts on the fee) rather than as payments, and are typically graduated: the more serious the failure to meet the level, the higher the penalty. They almost always have a cap (often a percentage of the period's fee). And, like delay penalties, they raise the question of whether they are the only remedy or accumulate with others, and whether in serious cases they give the right to termination. The principles of proportionality and validity we have seen apply here too: an SLA penalty disproportionate to the real damage of the disruption runs the same risks. If your contract revolves around service levels, our calculator on SLAs and uptime is complementary to this one and helps you reason about the technical part (availability, allowed downtime), while this one focuses on the penalty and its validity. This is a parametric estimate, not legal advice.

Penalty, deposit and termination clause: the differences

The delay penalty is only one of the many contractual tools that address breach, and it is often confused with others. Clarifying the differences helps to use them well. The table compares them:

ToolWhat it doesWhen it operates
Penalty (liquidated damages)Fixes in advance the amount owed for a breachWhen the breach occurs (e.g. delay)
Deposit / earnest moneySum paid in advance as a guaranteeCan be retained/doubled depending on who breaches
Termination clauseAllows dissolving the contract for a given breachWhen the specified breach occurs
Damages compensationCompensates the loss actually provenMust be proven in court (except the penalty)

They are different tools with different functions. The penalty quantifies in advance how much is owed for a breach, avoiding having to prove the loss — it is what this tool calculates. The deposit (or earnest money) is a sum paid in advance that acts as a guarantee: depending on the type and on who breaches, it can be retained or have to be returned in an increased amount; it operates at a different moment and with a different logic than the penalty. The termination clause does not fix an amount, but gives the right to dissolve the contract when a certain breach occurs — it is an «exit» remedy, not a compensation one, and often combines with the penalty (you collect the penalty and terminate). Ordinary damages compensation, finally, is the general remedy: it compensates the loss actually suffered, but must be proven in court — and it is exactly what the penalty saves you from having to do. These tools often coexist in the same contract and must be coordinated: understanding how they interact (does the penalty exclude further compensation? does it accumulate with termination?) is an essential part of good drafting. The calculator focuses on the penalty; the other tools require their own assessments. This is a parametric estimate, not legal advice.

Questions to ask before signing a penalty clause

Before accepting (or proposing) a penalty clause, some questions help assess it and avoid surprises. Is the amount proportionate to the expected real damage? It is the key question: a penalty anchored to a reasonable estimate of the loss is solid; a disproportionate one is at risk. Is there a cap, and how much is it? A reasonable cap protects the performer and strengthens validity. When does the delay start running and how exactly is the penalty calculated? The definitions matter as much as the numbers. Is the penalty the only remedy or does it accumulate with compensation for further damage and with termination? It is one of the most important and most overlooked clauses. What is the governing law, especially in an international contract? It determines whether an excessive penalty would be voided (common law) or reduced (civil law). Is the penalty symmetrical or does it hit only one party? Are there force majeure causes or extensions that suspend the penalty? Is the amount graduated by gravity or a single number for everything? If you are signing as the party that might have to pay, assess the maximum exposure (the cap) relative to the contract value and margin. If you are proposing the clause, make sure it is defensible and not just intimidatory. The calculator helps you quantify the amount and test proportionality; the other questions complete the picture. To draft or negotiate, get the assistance of a lawyer. This is a parametric estimate, not legal advice.

Frequently asked questions

What is a liquidated damages clause?

It is an amount agreed in advance that one party must pay the other in case of breach, typically a delay in delivery or performance. Its function is twofold: it avoids having to prove the loss suffered in court (the amount is already fixed) and gives certainty to both parties. In many contracts it also works as a cap on compensation. It is used in construction, supply, IT contracts, procurement and M&A.

How is the delay penalty calculated?

You multiply the daily penalty by the days of delay, then apply the cap. In this calculator: daily penalty = contract value × daily percentage; accrued penalty = daily penalty × days; penalty owed = minimum of the accrued penalty and the cap (value × cap%). The calculator also shows the share of the contract and the days beyond which the cap kicks in.

What data do I need?

Five values: the contract value, the daily penalty (as % of value per day), the days of delay, the cap (as % of the contract value), and the estimated actual damages from the delay. The first four are used to calculate the amount; the estimated damages are used to assess whether the penalty is proportionate and thus valid.

What is the difference between liquidated damages and a penalty?

It is the key legal distinction. A "liquidated damages" clause (legitimate) is a reasonable pre-estimate of the loss expected from a breach: it has a compensatory function and is valid. A "penalty" (in the pejorative sense) is a disproportionate amount with an intimidatory/punitive, not compensatory, function. The criterion looks at the estimate at the time of signing, not at what happened afterward. A penalty risks being struck down (voided or reduced).

Does the calculation depend on the currency?

No. The calculator is currency-neutral: enter the contract value and damages in your currency, while the daily penalty and cap are percentages. Delay penalty clauses exist in every legal system and every country: the legal treatment of an excessive penalty changes (common law vs civil law), but the logic of the calculation and of proportionality is universal.

How do common law and civil law treat an excessive penalty?

Differently. In common-law systems (UK, US and similar) the "penalty doctrine" applies: a disproportionate penalty is considered a "penalty" and is not enforced — an "all or nothing" approach. In civil-law systems (much of continental Europe, Latin America) the clause remains valid but the court can reduce it to a fair amount. In international contracts, the governing law determines which regime applies.

What is the cap for?

It protects both parties. For the performer, it limits the exposure: the penalty will not exceed a certain threshold however long the delay. For the one commissioning, it helps validity: an unlimited penalty appears more easily punitive. Beware the flip side: once the cap is reached, every further day of delay costs no more penalty, and the harmed party might prefer to terminate the contract. The calculator shows after how many days the cap kicks in.

Does the penalty also limit my compensation?

Often yes. In many legal systems and contracts the penalty also works as a cap on compensation: if the real loss is higher than the penalty, you cannot (barring different provisions) claim more. That is why a penalty that is too low, though valid, can make you waive part of the compensation in advance if a delay can cause much greater damage. Calibration is a balance between deterrence and actual recovery.

Why does the ratio between penalty and actual damages matter?

Because it is the proportionality test that decides validity. The penalty should be a reasonable estimate of the expected loss. Ratio close to 1 = proportionate, valid almost everywhere. Up to ~2 = reasonable. Over 2-4 = at risk (void in common law, reduced in civil law). Enormously disproportionate or almost nil damages = high risk of being classified as a punitive penalty. The calculator shows you where you stand.

When does a penalty risk being invalid?

When it is manifestly disproportionate to any foreseeable loss; when the expected damages were almost nil at signing; when it hits every breach, even minimal, with the same high amount; or when a cap is missing and it can grow indefinitely. It is strengthened by: an amount anchored to a documented estimate of the loss, a reasonable cap, a graduation, and consistency with the value/risk of the contract. Always keep a written record of the reasoning about the amount.

In which contracts is the delay penalty used?

In very many. The most classic case is procurement and construction (delay in completing the work, per day). Then supply and sale (delay in delivery), IT and software contracts (delay in release, failure to meet SLAs), services and outsourcing (deadlines), M&A (delay in closing), events and production (delivery on a fixed date). In every context the same principles of proportionality and validity apply.

How do I draft a good penalty clause?

Anchor the amount to a documented estimate of the loss; provide for a reasonable cap; graduate the penalty for delays of different gravity; be clear about the mechanism (start, calculation, application); clarify whether the penalty is exclusive or accumulates with further damages; consider the governing law in an international contract; and avoid amounts that appear punitive. The golden rule: a good penalty should not "scare" but credibly compensate a foreseeable loss. Get the assistance of a lawyer.

Is the result reliable?

It is a parametric estimate of the amount and an indicative assessment of proportionality, not legal advice nor a prediction of how a court will decide. The model simplifies (daily penalty × days with a cap; assessment on the ratio to damages alone). The real legal qualification depends on many factors (wording, governing law, case law, circumstances). The estimated damages are the most subjective element. Use it for the order of magnitude and the risk profile, then turn to a lawyer.

Updated July 2026

Formula

P_g = V\cdot\dfrac{d}{100},\quad L = \min\!\left(P_g\cdot g,\ V\cdot\dfrac{k}{100}\right)